- work plan and connections were costed and are agreed
- first new components will be ordered during next two weeks
- distribution cabinets are available
- installation work is schedule for different parts of SR1
- installation work will start end Oct beg. November
2 Pumps (under false floor):
img_5201
Heat Exchangers:
img_5202
installation of manifolds:
img_5207
Electrical connection to pumps
- 55 racks are installed in final location
- heat exchangers (for water colled racks): pressure tests are finished
- heat exchangers will be installed in final location soon
5 rows of installed racks
img_5204
img_5205
Cooling manifolds in racks
img_5208