Meeting SR 27-Nov 2002
Discussion on services routing in SR
Minutes
Service installation:
Richard proposal was found ok. It details the number and size of cable trays
and their location.
The trays will be fixed by metal strips on the main upper support beam.
All trays will start above the diffusers.
Depending on confirmation by ST, we propose to have the installation done
by Schultess, which are currently mounting the wall panels of the clean room.
We would ask them to
= install the metal strips to support trays and pipes
= install the cable trays
= install the clips for pipes
We will supply all necessary material for the installation.
Richard will prepare an inventory for quotation and material cost estimate
and order parts if ok. This includes a layout plan which can be used by Schultess
for installation
Heinz will check with ST if this work can be done by Schultess, and arrange
for possible time slots.
Preparation for pipes:
we will mount clips that allow a simple installation of pipes without further
drilling in the wall.
The evap cooling system pipes (with insulation) will be laid in trays. The
actual pipes for gas can be installed later.
Evaporative cooling system:
It was proposed by Michel Bosteels to have a simpler distribution with all
manifolding inside the thermal enclosure. This would significantly simplify
the cooling system. For the final system this means 4 entry points of cooling
services (one each corner of the ID trolley, 2 entry points for ECs)
Each entry point will have one assembly of heat exchanger and heater, which
is _part of the ID trolley and service support_ . This part needs to be implemented
into the service support and temporary enclosure during the tests.
This needs to be clarified for mechanical constraints with Marco, Eric and
Andrea.
Information material from
Anatoli: TRT services routing
Vic: Evaporative cooling in SR
Richard: SCT service in assembly area, type