Wall panels for clean room walls and ceiling are delivered. They
will be mounted during the next 3 wks by Schultess.
Ventilation: extraction air-ducts delivered
Ventilation: Mono bocks airhandling unit was delivered to CERN.
Doors to clean room:
Doors have been mounted by IDEA, Italy. Some correction to the doors were necessary and were carried out by IDEA. We have all doors (3 large+3small) mounted.
Ventilation: Main electrical control cabinet mounted in SR1 building
Ventilation: Main inlet airducts now connected through the wall towards the airhandling unit.
Clean room:
First stretch of clean rooms walls are mounted. The diffusers are mounted and sealed in the wall.
img_5623
img_5624
img_5625
img_5626
Ventilation: Air handling unit installed on the concret slab behind
the building.
The installation of the airducts to the AHU is progressing at the moment.
The airhandling unit is currently being cabled by ZVVZ to the main electrical
control.