Status of installation of clean room in SR1 on 5/12/02
The following pictures show the installation of clean room walls (joints
along corners will be seal at very end of installation).
(Click to enlarge)
Installation of walls and air diffuser through control room is finished
Installation of walls and diffusers in clean room test area is finished
Installed clean room walls and diffusers in assembly area ( this view
is from the test area towards the assembly area. In the foreground the test
area concrete platform is visible (6.9x6.2m)
Installation of extraction airducts on clean room roof has started