SR1 Status and integration discussion 30-31/10/02

 

 
 
 

Integration Discussion 30/10/02


Subject: Time periode mid -2004 to end 2005 (end of phase 2 - start phase 3)


(Click to enlarge)
 

Area Numbering for this discussion:


Note, that the rest of the assembly area is used for other activities, which where not part of the discussion (that they are white doesn't mean they are empty) !
 

A sketch of the schedule outline:

img_5299
 

We agreed to study the feasability of the following  baseline program and space sharing:

    2005:

  1. all final tests of ID barrel, EC A and EC C must be done in the test area
  2. ID SCT -> TRT barrel are assembled (insertion) in TA
  3. ID barrel is tested in TA
  4. ID EC C: SCT->TRT is assembled in the area 1
  5. ID EC C is moved to TA when barrel is finished
  6. ID EC C is tested in TA
  7. ID EC A is assembled in area 1
  8. ID EC A is moved to TA when EC C is finished
During operation 1 to 8 the entrance to the test area is from area 1 (original planned door), the TA is separated from the assembly area by a fence . Area 3 is used continously by pixel. (TRT and SCT endcap A's will be continued in specific TRT and SCT area (sct: area 2, trt: area right of area 1) )

We will look into possibilities to test ID EC A and C  (after sct->trt insertion) in parallel.

    2003 to mid 2004

  1. SCT barrel visual inspection is done in area 2
  2. SCT barrel acceptance tests are in TA
  3. SCT 4- barrel assembly is in area 2
  4. TRT barrel structure alignment is done in TA (full platform for 1 month sometimes during Sept/Nov 03)
  5. TRT barrel module mounting & testing is done in area 1 (upper half, needs further study),
  6. TRT EC tests are done in area 1 lower half
  7. pixel will require 12x4m area for trial-assembly for 3 months at end 2003/early 2004 anywhere in the assembly area
  8. during this full periode the pixel do not require their full area adjacent to the TA and space up to axis 11 can be used (left half or area 3)
  9. during this periode (2003-mid 2004, operation 1-9) the access to the TA will be through the pixel area (left part of area 3)
    mid 2004-end 2004:
  1. full SCT services are installed in TA (while 4-barrel assembly progresses)
  2. TRT barrel will be moved to TA when finished and be prepared for SCT barrel
  3. SCT barrel moves to TA when finished
  4. SCT EC C acceptance tests are done in area 2
  5. TRT EC C testing coninues in lower half of area 1
Note that during the periode mid 2004 to end 2004 we will move the entrance to the TA back from area 3 to area 1 .

Next steps

Status of SR1 building 31/10/02

Clean room walls


The C-profiles to hold the walls on the bottom and the side are all welded in.
The walls will arrive at Cern during next week.

img_5300
img_5301
 

Ventilation:
the air-ducts for the clean room ventilation extraction have been dilvered by ZVVZ
img_5302

the hole for the main extraction duct is being drilled in the out side building wall
img_5303

the hole for the main air inlet of the ventilation in the building wall is finished, the wall is reinforced by beams above the holes, the inlet connection for the air ducts below the false floor is visible in the forground.

img_5304
img_5308
 inlet hole from out side (the air ahndling unit willbe placed in the concret slab to the right)
img_5307
drilling of the extraction hole. This hole will also serve for the emergency smoke extraction of the area

ZVVZ started the installation of the diffusers in the clean room (to be finished this week)
img_5305

The main airhandling unit and the controls will be delivered to Cern next week.
 

Electricity


The first transformer (on the picture below to the right) will stay and serve as the main electricity supply (precisely speaking not this one, but another one in its place)
This arrangement was made to save money for the main connection of the elctricity distribution cabinets . They are right behind the building wall (which saves substantial high power cabling between the transformer and the distribution)

The other transformers along this wall can be removed to allow for the installation of baracks. Those baracks will (most likely) serve for the evaporative (maybe also mono) cooling , gas supply for PIX,SCT,TRT,  .

img_5306
 

The installation of the electricial distribution will start next week.
The reinforcement of floors for electrical distribution cabinets and UPS in the rack area is finished.
The drain infornt of the laser room outside door (later blocked) is being installed right now.