SR1 status 21/02/03

1.) Ventilation system

The ventilation system is fully installed and commissioned by ZVVZ. The official handover to ST/CV was 20/2/03. The unit is operational. It will be switch on then the clean room has been cleaned.

(pictures below)

2.) Floor

The floor has been polished an leveled. All panels have been fixed against support beams. The antistic floor and grounding strips have been laminated on. All floor mats are glued and sealed.

This item is ready

(pictures below)

3.) Detection incendie

all safety detection sensors are installed. all smoke sniffer pipes are installed and connected.

Smoke sensors are installed inside the clean room (2 pipes along the room) and below the flase floor (3 pipes along the building)

The installation for the safety system has been finished. The system will be connected to TCR and fire brigade in 1 week.

The installation is finished.

4.) Emergency smoke extraction

(see pictures)

The installation of airducts and extraction units is completed. The smoke extraction will be electrically connected within the next two week.

The site was visited by the firebrigade. Smoke extraction and the installed detection incendie will be tested with a smoke test by the firebrigade and TIS in the clean room before the clean room is cleaned out (approx 3 wks).

5.) Walls

All installation of clean room , control room , laser room walls is finished. This includes joint covers, blinds and grids. This work by Schulthess is finished

6.) Clean room

A few damaged panels have been removed and new panels have been installed. Lights in the clean room are installed. All floor work in the clean room is finished. The remaining items for the clean rooms are the installation of AC outlet and network outlets.

========= the clean room will be cleaned out in 4 weeks and locked =========

====== the clean room will be closed and locked at end of March  ======

 

7.) Control room

A small air lock from control room to the clean room will be installed in the 2 weeks. Additionally a window will be installed between the control room and the test area to allow visual contact. The air-conditioner for clean room arrived and will be installed next week.

8.) Electricity installation

(see pictures below)

At the moment 3 persons work continuously in SR1 on the electricity installation. Priority is given to assembly area and test area (in order to close clean room as soon as possible).

The rack electricity installation (canalis rail system ) has be finished by friday

The installation of lights in assembly/test area is finished. Lights in the laser room still need to be done.

The main transformer station for our installation (dry transformer) has been delivery and installed in place at the rear of the building. The transformer is connected and operational.

The high power wiring from the transformer station to the distribution is finished.

The electrical distribution to the ventilation is finished and runs.

The installation and execution plan for the installation of cable trays in the clean room is ready. Their installation has to wait until all other work on electricity is finished and has to be planned separately with ST/EL.

1 UPS has already been moved to SR1, the other one will be moved during the next two weeks. After installation both UPS will be inpected for operation by Siemens.

The remaining work is: finish distribution, installation of AC outlet, some remaining lights, installation of UPS and grounding of wall panels, antistatic floor connections and connection to the smoke extraction. The remaining work is estimated to take another 3 weeks.

9) Network

A site visit was done on 21/2/03 to clarify open question regarding the installation of the net work cables. The fibre connection arrived. The installation work on the network cable is scheduled to start March 15.

10.) Other items

Door locks:

most door locks are installed. the lock for the double door to the rack area needs to be installed. At present 2 keys are available (contact R. Fortin, H. Pernegger). Remaining door frames/wings will be stored in Bat 175.

 

IMG_6120.JPG
lamination of antistatic floor

IMG_6121.JPG
lamination of antistatic floor

IMG_6359.JPG
finished antistatic floor

IMG_6360.JPG
finished antistatic floor

IMG_6127.JPG
wiring electricity connection to outside transformer

IMG_6355.JPG
mounting of electricity switch board

IMG_6126.JPG
cabling of electricty distribution

IMG_6356.JPG
cabling of electricty distribution

IMG_6365.JPG
finished ventilation unit

IMG_6358.JPG
commissioned ventilation control

IMG_6361.JPG
installation of emergency smoke extraction

IMG_6362.JPG
installation of emergency smoke extraction

IMG_6364.JPG
installation of emergency smoke extraction