Pictures taken in SR1 on 05-Feb-02

(click on pictures to enlarge)

Metal frameowrk for assembly area (AA), test area (TA) and laser area (LA);


The metal frame work to hold the clean room walls are being mounted

view towards main entrance to AA, where the air-lock will be located
dscn3058
view from AA towards the test area (TA)
dscn3059
 

Platforms:


View of the CMM concret slap (foreground), as being put in today, and the TA concret slat (background)
dscn3060\

Floor opening below the control area. the volume underneath is cleared out of any pillars. (For a simpler 1 unit AHU system, the AHU will now be located outside the building).
dscn3061

Conret slap behind SR1 to house the 1-unit AHU ventilation system. Note that the door will later be blocked by the clean room wall.
dscn3065

End of exisitng platforn behind building: Proposed area for gas-batteries on this side of the building (SCT,PIX). There is a similar one above the technical gallery on the other side for TRT. Need to check which/when trnasformers will be moved.

dscn3066
 

Rails:


Rail structures underneath the assembly area (AA) false floor. Note that cable trays are mounted in some but not all corridors. Some of those structures will be removed during the installation of the air ducts
dscn3063
 

Rail structure under the AA floor along the side-wall of the AA. The panel which is taken out in this photo will later be partially covered by the clean room wall. Need to verify in the latest drawings for the AHU-ducts, if the ducts will replace some of the rails (left pitcure side) or run in the corridor adjacent to it (right side of picture).
dscn3064
 

dscn3067