SR1 status (22/10)
1.) Ventilation
-
finished installation of air ducts below the floor
-
ventilation mono-block and its control is about to be ready in Prage for
testing
-
holes in main building walls will be drilled next week (holes to connect
airducts to mono-block outside of building)
-
crane electrical 0/1 switch will be moved by R. Necca as this is in the
place of one of this holes now
-
connection to cold-water supply (Gematec) ordered
-
ventilation installation will cont. in November
2.) Clean room walls
-
installation of support profile rails for clean room walls has started
-
Double door frames are in area now (not yet mounted)
-
NOTE: lower beam of double door frame has to be lower than floor level.
This is necessary to avoid steps at the door.
3.) Electricity
-
Installation of support for electrical distribution cabinets and UPS has
started and is nearly finished
-
Installation of electrical cabinets will start in 1-2 wks.