SR1 status 5/12/02


Status of installation of clean room in SR1 on 5/12/02
The following pictures show the installation of clean room walls (joints along corners will be seal at very end of installation).


(Click to enlarge)

Installation of walls and air diffuser through control room is finished

  IMG_5707

Installation of walls and diffusers in clean room test area is finished


IMG_5708

Installed clean room walls and diffusers in assembly area ( this view is from the test area towards the assembly area. In the foreground the test area concrete platform is visible (6.9x6.2m)

IMG_5709
IMG_5710

Installation of extraction airducts on clean room roof has started

IMG_5711
IMG_5712